Hello Krushna,
In ref to trail mail, while developing the CAP module, we need to apply following validations
CAP is applicable in both cases as below
For conditional certificate (Up to 2 Major NC other than social requirements) CAP need to submit within 7 days
Normal CAP-Other than Major NC which need to submit within 14 days
Kindy note that currently don’t apply any auto restriction functionality as per above days
Rather, highlight if timeline is crossed by any certification request and show tab for "CAP Due Date:______" (calculate the cap due date from the audit end date by CB)
If any clarification required, please let me know, and please share the timeline to complete the pending points
Regards,
Suresh
Updated by Admin Admin 5 months ago
As per the discussion with Gaurav we will implement this afte GE tool implementation